DEJOR Production & QC Factories
Eight factories, floor by floor.
We run three factories of our own: a sweater factory in Zhangjiagang, China, and two in Myanmar. This page walks through eight sites in Myanmar and Vietnam, two of them our own and six long-term partners, making knitwear, wovens and outerwear. First what each one does on site, then two of them up close, then a walk through the floors in the order your goods move through them.

The eight factories
Myanmar
6
factories, two of our own (MM-2, MM-3) and four long-term partners, for knitwear, sweaters, wovens and outerwear.
-
Knitwear
Linking · Sewing · Washing · Pressing · Packing
-
-
Wovens & outerwear
Cutting · Sewing
-
Knitwear
Knitting · Sewing · Washing
-
Knitwear
Knitting · Sewing · Washing · Pressing · Packing
-
Wovens & outerwear
Cutting · Sewing
Vietnam
2
long-term partner factories, for wovens, jersey and knit activewear.
-
Wovens & jersey
Cutting · Sewing · Packing
-
- Also working with us A knitwear factory in Cambodia and another factory in Vietnam On Production & QC
The processes listed are the ones in our photos of each site. Our own factories are in China and Myanmar; we also work with long-term partner factories in China, Myanmar, Vietnam, Bangladesh and Cambodia.
Up close · MM-2 · Our sweater factory in Myanmar
From yarn cone to carton, under one roof.
MM-2 knits, links, washes, presses and packs sweaters from 3 to 18 gauge. Yarn and trims are checked and tested on arrival, and the factory softens its own water for the wash and treats the waste water before it leaves the site.
- Workers
- 2,200
- Plant area
- 18,583m²
- Pieces a month
- 500,000
- Computerized knitting machines
- 100
- Linking machines
- 2,000





28 steps, 10 checks of every piece.
The quality route MM-2 works to, from yarn in to the quality review at the end. On top of these checks, the factory QC inspects on the line twice and again after packing, and our own QC checks the goods against the approved sample.
- Yarn and trims in
- Check and test (every piece)
- Into the store
- Issued to the floor
- Pre-production meeting
- Knitting
- Panel check (every piece)
- Linking
- Linking check and mending (every piece)
- Hand stitching
- Stitching check (every piece)
- Cleaning (every piece)
- Light check before washing (every piece)
- QC in-line inspection (QC)
- Washing
- Light check (every piece)
- Ironing
- Check and mending (every piece)
- Label sewing
- First check (every piece)
- Mending
- QC in-line inspection (QC)
- Final check (every piece)
- Metal detection before packing
- Packing
- Metal detection after packing
- QC final inspection (QC)
- Quality review meeting
Up close · VN-2 · Partner factory in Vietnam
Fifteen lines for knit activewear.
A long-term partner in northern Vietnam, about two hours by road from Hanoi airport and three from Haiphong port. It makes pullovers, hoodies, joggers, polos and T-shirts, with its pattern, fabric inspection and test rooms next to the lines.

- Sewing lines
- 15
- Workers per line
- 20–22
- Production area
- 13,000m²
- Pieces a month
- 650–850k






Figures are the factory's own. Our patterns and spec travel with the style, and our QC works on this floor during production, as in our own factories.
Walk the floor
From fabric in to cartons out.
-
01
Fabric in
Rolls are checked in by lot and run over the inspection machine before they reach the cutting table.

MM-6 · Myanmar 
VN-1 · Vietnam 
MM-5 · Myanmar -
02
Cutting
Panels are cut from the pattern files made in our Zhangjiagang sampling center, on automatic cutters or spread and cut by hand.

MM-6 · Myanmar 
VN-1 · Vietnam 
MM-6 · Myanmar -
03
Knitting & linking
Computerized flat knitting machines knit the panels to shape. Linkers then join them loop by loop.

MM-4 · Myanmar 
MM-5 · Myanmar 
MM-2 · Myanmar -
04
Sewing
Lines are set up style by style. Our QC checks pieces on the line.

MM-6 · Myanmar 
VN-1 · Vietnam 
MM-6 · Myanmar -
05
Washing & pressing
Knitwear is washed and dried for hand feel, then steamed and pressed to the size spec.

MM-5 · Myanmar 
MM-1 · Myanmar 
MM-5 · Myanmar -
06
Final check & packing
Finished garments are checked against the approved sample, packed to your packing list and held until you release the goods.

MM-5 · Myanmar 
VN-1 · Vietnam 
MM-5 · Myanmar
Factory questions buyers ask first.
Where are your factories?
We have three factories of our own: a sweater factory in Zhangjiagang, China, and two factories in Myanmar. We also work with long-term partner factories in China, Myanmar, Vietnam, Bangladesh and Cambodia. This page shows six factories in Myanmar, two of them our own and four partners, and two partner factories in Vietnam. The knitwear factory we work with in Cambodia and another factory in Vietnam are on our Production & QC page.
What do the factories in Myanmar make?
Mostly knitwear. Four of the six make sweaters and other knitwear, from knitting and linking to washing and pressing. The other two cut and sew wovens and outerwear.
Which factory will make my order?
We suggest one based on the fabric and construction, the quantity, the delivery date and where the goods ship. We explain the suggestion with the quote, and you approve it.
How do you keep quality the same across factories?
Patterns, grading and the workmanship spec are made in our sampling center in Zhangjiagang and travel with the style. Our QC reports from the line during production, and the goods are checked against the approved sample before they ship.
How long does bulk production take?
Bulk usually takes 30–45 days after the pre-production sample is approved and the fabric is in. We confirm the date in writing for each order.
Plan your production
Tell us the style. We suggest the floor.
Send a tech pack, a reference garment or the styles in your sample basket, with quantities and the delivery window. We reply with a factory suggestion and the next steps.